Skip to main content

menu
Fuel Pump Room and Fuel Tank Removal

Fuel Pump Room and Fuel Tank Removal

Existing fuel tank removal and excavation for new tower foundations will commence upon start-up of the fuel supply system. This is anticipated to start the last week of March.

Fuel Pump Room work continues along the south side of the existing South Addition. Crews continue with the equipment fit out of the room. 

Selective demolition of portions of the South Building is ongoing. 

All of these activities are expected to create typical levels of construction noise and truck traffic.

Fuel Pump Room and South Building Demolition

Fuel Pump Room and South Building Demolition

Fuel Pump Room concrete work continues along the south side of the existing South Addition. Crews continue with forming, installing reinforcing and placing concrete at these locations.

Selective demolition of portions of the South Building is ongoing. 

Typical levels of construction noise and truck traffic can be expected with all of these activities.

Trench Backfilling and Fuel Pump Room

Trench Backfilling and Fuel Pump Room

Installation of the underground fuel lines from the tanks to the Fuel Pump Room is now complete and backfilling of trenches is underway. Crews are also continuing to install reinforcing and place concrete in the Fuel Pump room and the concrete floor will be installed early next week.

Demolition of the two story portion of the South Building continues. 

All of these activities are expected to create typical levels of construction noise and truck traffic.

Tower Crane Foundation Installation

Tower Crane Foundation Installation

Installation of reinforcing for the Tower Crane foundation is underway. A small crane will be setting the anchors for the Tower Crane, then construction of the concrete pad will follow.

Fuel Pump Room concrete work is underway along the south side of the existing South Addition. Crews continue with forming, installing reinforcing and placing concrete at these locations.

Excavation and installation of the underground fuel lines from the tanks to the Fuel Oil Pump Room are underway and anticipated to continue through next week.

All of these activities are expected to create typical levels of construction noise and truck traffic.

Fuel Line Installation

Fuel Line Installation

Excavation and installation of the underground fuel lines from the tanks to the Fuel Pump Room are underway and anticipated to continue through next week.

Concrete work for the Fuel Pump Room is underway along the south side of the existing South Addition. Crews continue with installing, reinforcing, and placing concrete at these locations. 

Demolition of the two-story portion of the South Building is ongoing. This is anticipated to continue through the first week of March.

Installation of reinforcement for the Tower Crane foundation is also underway. All of these activities are expected to create normal levels of construction noise.