Fuel Line Installation
Excavation and installation of the underground fuel lines from the tanks to the Fuel Pump Room are underway and anticipated to continue through next week.
Concrete work for the Fuel Pump Room is underway along the south side of the existing South Addition. Crews continue with installing, reinforcing, and placing concrete at these locations.
Demolition of the two-story portion of the South Building is ongoing. This is anticipated to continue through the first week of March.
Installation of reinforcement for the Tower Crane foundation is also underway. All of these activities are expected to create normal levels of construction noise.
Global Administrator |
2/12/2021
You may also like