MRI Replacement Project
The MRI Replacement Project, which began in September 2019, remains on schedule.
The new MRI equipment was delivered last Friday and installation began on Saturday. The temporary wooden stairs on Bellevue Drive have been removed and the window has been replaced. On Thursday, Jan. 30, weather permitting, roofers will patch the steel support above the new MRI between 7 a.m. and 3 p.m. They may utilize a torch to melt the snow and ice; a smoke eater will be placed on the roof to filter the air around the torch when in use.
The new MRI equipment should be ready for use on March 1.
North Lot Wall Update
The North Lot Wall Project continues to move forward. To maintain the integrity of the wall, additional supports have been designed. The material to complete these supports is on order and expected by mid-to-late February.