Saturday Work 5/7
Crews will be on site Saturday 5/7 from 7 a.m. to 5 p.m. Work will include exterior framing and sheathing plus fireproofing structural members, framing and plumbing inside the shrink wrapped building.
During the week, the tower crane and buck hoist (temporary exterior elevator) will be used for construction activities onsite. Crews will be fireproofing on the 4th floor and in the mechanical penthouse. They will also be installing interior and exterior framing on the 5th, 6th, 7th floors, and the mechanical penthouse using the swing stage scaffolding and drywall top fill on the 5th and 6th floor for mechanicals. Roof demo and curb prep will be taking place for the new boiler room directly above the 2nd floor south, west corner of the Observation Unit.
Typical levels of construction noise and vibrations are expected with all of these activities. For the deep foundation work, any possible vibrations will be monitored by a third party testing agency.