No Work Saturday and Friday Parking in Mt. Vernon Cut Out

On Friday 10/7, contractors will be removing construction materials from the building in the morning. They will be loading out through the Mt. Vernon Access and to collection containers/vehicles parked within the short term parking area on Mt. Vernon. This activity should be completed by 10 a.m.

Construction Crews will not be working onsite this weekend.

South Building roofing work has been delayed, but is anticipated to start back up in the next week or so once the roofer acquires the Mount Vernon Permit for the crane.

Deep foundation, pile cap and grade beam installation is ongoing and will continue through early October. Excavation and grading work is happening at the same time as the deep foundation installations.

Construction of the ramped section of the South Access Drive to connect to Mt. Vernon is anticipated to start mid-November.  Fill material will be placed in “lifts” and compacted until the final grade height is reached.

The Tower Crane will be in full operation erecting the super structure steel. The crane will be running a little later to make up for the loss of morning day light.

Typical levels of construction noise and vibrations are expected with all of these activities. For the deep foundation work, any possible vibrations will be monitored by a third party testing agency.

Saturday Work 10/2

Crews will be onsite Saturday 10/2 continuing demolition on the South Addition from 7 a.m. to 4 p.m.

Deep foundation, pile cap and grade beam installation is ongoing and will continue through early October. Excavation and grading work is happening at the same time as the deep foundation installations.

Construction of the ramped section of the South Access Drive to connect to Mt. Vernon is anticipated to start mid-November.  Fill material will be placed in “lifts” and compacted until the final grade height is reached.

The Tower Crane will be in full operation erecting the super structure steel.

Typical levels of construction noise and vibrations are expected with all of these activities. For the deep foundation work, any possible vibrations will be monitored by a third party testing agency.

Saturday Work 9/25

Crews will be on site on Saturday, 9/25 from 7 a.m. until 4 p.m. working on demolition on the east elevation of the current south addition. This is anticipated to create typical levels of construction noise.

Deep foundation, pile cap and grade beam installation is ongoing and will continue through early October. Excavation and grading work is happening at the same time as the deep foundation installations.

Construction of the ramped section of the South Access Drive to connect to Mt. Vernon is now anticipated to start mid-November. Fill material will be placed in “lifts” and compacted until the final grade height is reached.

The Tower Crane will be in full operation erecting the super structure steel.

Typical levels of construction noise and vibrations are expected with all of these activities. For the deep foundation work, any possible vibrations will be monitored by a third party testing agency.

No Weekend Work 9/18 or 9/19

This week deep foundation, pile cap and grade beam installation will continue and is expected to last through the end of September. Excavation and grading work is happening at the same time as the deep foundation installations.

Construction of the ramped section of the South Access Drive to connect to Mt. Vernon is anticipated to start at the end of September. Fill material will be placed in “lifts” and compacted until the final grade height is reached.

The Tower Crane will be operating to install the structural steel.

Micro Pile installation is now complete.

Typical levels of construction noise and vibrations are expected with all of these activities. For the deep foundation work, any possible vibrations will be monitored by a third party testing agency.

Saturday Work 9/11

Crews will be working on Saturday from 7 a.m. to 4 p.m. drilling and cutting into foundation walls on the south side of the building. An all-terrain fork lift will be used to perform this work along with a concrete saw and a generator. There will be no tower crane operations.

Deep foundation, pile cap and grade beam installation is ongoing and will continue through mid-September. Excavation and grading work is happening at the same time as the deep foundation installations.

Construction of the ramped section of the South Access Drive to connect to Mt. Vernon is anticipated to start in mid-September. Fill material will be placed in “lifts” and compacted until the final grade height is reached.

The Tower Crane will be operating to install the structural steel.

Micro Pile installation has resumed for a week or so to compete the balance of the piles. This will include excavations for the shoring being installed with micro piles.


Typical levels of construction noise and vibrations are expected with all of these activities. For the deep foundation work, any possible vibrations will be monitored by a third party testing agency.