October 2022

Saturday Work 10/29

Saturday Work 10/29

Crews will be onsite Saturday 10/29 from 7 a.m. to 5 p.m. working on installing windows and siding from the swing stage scaffolding along with possible roofing on top of the mechanical penthouse.

During the week, crews will continue working on drywall finishing and painting along with various mechanical installations inside the new tower. The tower crane will still be in operation moving materials from the ground to various floors of the building. The buck hoist will also be used to move people, equipment, and materials from floor to floor. Crews will be installing windows and siding on various elevations around the outside of the building. Roofing continues on the top of the mechanical penthouse.

These activities are expected to produce typical levels of construction noise but no vibrations.

Later in November, crews will be working to raise the pavement area next to the new tower to be the same level as Mt. Vernon Ave. This activity is anticipated to generate some minor vibration, and more details will be sent out via this blog as we get closer to this work occurring.

Saturday Work 10/22

Saturday Work 10/22

Crews will be onsite Saturday 10/22 from 7 a.m. to 5 p.m. conducting miscellaneous exterior work from the swing stage scaffolding, window installation on the east elevation, brick on the south side of the building, and roofing on the south building/tower penthouse.

During the week, crews will be using the tower crane and buck hoist for activities on site. Full height drywall and drywall finishing is happening on all floors. The prime and first coats of paint are being painted on floors where drywall is done. Mechanical, electrical, and plumbing rough ins continue throughout the building.  

Typical levels of construction noise and vibrations are expected with all of these activities. Any possible vibrations will be monitored by a third party testing agency.

Saturday Work 10/15

Saturday Work 10/15

Crews will be onsite Saturday 10/15 from 7 a.m. to 5 p.m. Miscellaneous work will be happening from the swing stage scaffolding including hunter panel installation and window installation.

During the week, the tower crane and buck hoist will be used for activities onsite. Full height drywall installation and drywall finishing continues on all floors. Primer and the first coat of paint is going in where drywall is finished. Mechanical, electrical, and plumbing rough ins continue throughout the building. Brick installation on the building is almost 90% complete. Roofing continues on the 7th floor and the mechanical penthouse. Miscellaneous crane picks continue for glass, window frames, etc.

Typical levels of construction noise and vibrations are expected with all of these activities. Any possible vibrations will be monitored by a third party testing agency.

Saturday Work 10/9

Saturday Work 10/9

Crews will be onsite this Saturday 10/9 from 7 a.m. to 5 p.m. working on hunter panel installation and window installation from the swing stage scaffolding.

During the week, the tower crane and buck hoist will be used for activities on site. Miscellaneous interior and exterior framing continue on the 5th, 6th, 7th, and mechanical floors. Full height drywall installation continues on the 6th, 7th, and mechanical penthouse floors. Prime and first coat of paint is happening on the floors where drywall is finished. Mechanical, electrical, and plumbing rough ins continue in multiple locations within the building. Brick installation continues on the exterior and roofing is happening on the 7th and mechanical penthouse floors.

Typical levels of construction noise and vibrations are expected with all of these activities. Any possible vibrations will be monitored by a third party testing agency.