There will be no outside work taking place on the MRI over the weekend. On Monday, October 28 there will be a delivery of rebar to reinforce the new concrete floor. Thursday, October 31 a concrete truck will be here around 11 a.m. to pour the first section of the floor, the truck will be here for about an hour. The truck will be parked next to the building and there will be noise from the truck and the pumping equipment. Also on Monday, October 28 a welding machine will be brought on site. It will be used off and on until November 7. The welder is anticipated to produce a low humming noise when in use.