There will be no construction work on site over Memorial Day Weekend.
Recent work on the hospital’s main garage will conclude tonight at 6 p.m. A couple of smaller repairs will take place in a few weeks during daytime hours only and the noise impact of those repairs should be minimal.
Micropile installation will resume on June 1 and will continue for approximately 3 weeks.
South Building roofing work has started and will last approximately 8 weeks. This work will include tear-off of the existing roof, installation of a new roof and installation of new HVAC equipment. It will require cranes for rigging materials and equipment to the roof. These will be staged in the Mt. Vernon cut out and will necessitate partial temporary road and sidewalk closures along Mt. Vernon. A flagger will be used during deliveries that could impact travel flow. The odor of melting tar can be expected from these activities.
Typical levels of construction noise and vibrations are expected with all of these activities. For the micropile and deep foundation work, any possible vibrations will be monitored by a third party testing agency.