Demolition and Fuel Pump Room
Demolition of portions of the South Building is ongoing and commissioning of fuel pumping equipment should be completed by the end of March.
Existing fuel tank removal and excavation for new tower foundations will start after the new fuel supply system is fully operational. This is anticipated to begin the last week of March/early April. Micropile installation is also expected to resume in mid-April.
Typical level of construction noise and vibrations are expected. Vibrations will be monitored by a third party testing agency during micropile installation.
Global Administrator |
3/26/2021
You may also like