Weekend Work 6/11 and 6/12
Crews will be on site on Saturday 6/11 from 7 a.m. to 5 p.m. Work will include fire proofing the structure inside the shrink wrapped building, plumbing pressure testing, and exterior framing.
A partial crew will also be on site Sunday 6/12 from 7 a.m. to 2 p.m. conducting plumbing pressure testing inside the shrink wrapped building.
During the week, the tower crane and buck hoist will be used for construction activities. Fire proofing will be happening on the 4th floor. Interior and exterior framing will be happening on the 5th, 6, 7th floors, and the mechanical penthouse. Drywall top fill will be installed on the 5th and 6th floors. Mechanical, electrical, and plumbing rough ins will also be installed in multiple locations within the building.
Typical levels of construction noise and vibrations are expected with all of these activities. For the deep foundation work, any possible vibrations will be monitored by a third party testing agency.
Global Administrator |
6/9/2022
You may also like