Skip to main content

menu
URMC / Highland Hospital / Facilities / Blog / January 2022 / Saturday Work 1/15

Saturday Work 1/15

Crews will be on site Saturday 1/15 working on the structural steel and detailing decking on the upper floors from 7 a.m. to 4 p.m. (weather dependent). Concrete workers will also be on site covering the 2nd floor newly poured slab with concrete blankets.

During the week, the tower crane will be in operation building super structure steel as the steel workers detail decking on the upper levels. Crews will also be pouring the second floor concrete slab on Friday 1/14 starting at 7 a.m. and pouring the third floor concrete slab on Tuesday 1/18 (weather dependent). Concrete finishing has the potential to run later into the day, but the building wrap should isolate any potential impacts to the neighborhood. Mechanical hangers are being put in on the 6th, 7th and 8th floors new decks for future installation of the mechanical piping.  The stair risers are being filled with concrete for easier access from floor to floor. Temporary building enclosure is happening using ZAP wrap. New tower 7th floor temporary roofing will be installed starting the week of January 17th (weather dependent).

Typical levels of construction noise and vibrations are expected with all of these activities. For the deep foundation work, any possible vibrations will be monitored by a third party testing agency.

Global Administrator | 1/13/2022

You may also like

No related posts found.