Skip to main content

menu
URMC / Highland Hospital / Facilities / Blog / January 2021 / Fuel Pump Room and South Building

Fuel Pump Room and South Building

Fuel Pump Room concrete work is underway along the south side of the existing South Addition. The Fuel Pump Room is scheduled to be complete and operational by the end of February, early March. Crews continue with forming, installing reinforcing and placing concrete for this portion of the project.

Excavation and installation of shoring for the tower crane pad concrete base is nearly complete. Micropiles for the foundation will be drilled into place next week with installation of reinforcement to follow, then the concrete pad will be poured. Regular levels of truck and construction noise can be expected for all of these activities.

Global Administrator | 1/28/2021

You may also like

No related posts found.