Excavation and installation of shoring for the tower crane concrete base is complete. Micropiles for the foundation have been drilled into place and shoring attached. Installation of reinforcing and anchors will begin next week. A small crane will be setting the anchors in place on March 16, before placement of the concrete pad. Noise from this is expected to be minimal and include engine noises, back up alarms, and heavy equipment tracking around the site.
The Fuel Oil Pump Room concrete work is underway along the south side of the existing South Addition. The Fuel Oil Pump Room is scheduled to be complete and operational by the end of February, early March. Crews continue with forming, installing reinforcing and placing concrete at these locations.
Demolition of the two story portion of the South Building continues with normal levels of construction noise.