Fuel Oil Pump Room Construction
The second fuel tank installation is now complete. Excavation for the Fuel Oil Pump Room foundation is underway along the south side of the existing South Addition. Work on this part of the building will include drilling micropiles and pouring foundations, which will begin the week of December 28. This work is anticipated to create minimal noise.
Demolition of the former discharge ramp has resumed and is anticipated to last for three more weeks. This work will include the sound of trucks backing up.
No work is scheduled for December 25, 26, 27 or January 1, 2, and 3. Crews will be working no later than 3:30 p.m. on Christmas Eve and New Year’s Eve.
Global Administrator |
12/23/2020
You may also like