Saturday Construction 8/21

Crews will be working on Saturday, 8/21 from 7 a.m. to 4 p.m. Work will include striping foundation forms. Activity will include fork lifts and banging noises from the stripping process. There will be no tower crane operations during this time.

This week’s work will include the Tower Crane lifting stub columns onto the third floor roofs.

Micro Pile installation has resumed for a week or so to compete the balance of the piles. This will include excavations for the shoring being installed with micro piles.

Deep foundation, pile cap and grade beam installation is ongoing and will continue through mid-September.

Construction of the ramped section of the South Access Drive to connect to Mt. Vernon Ave. is anticipated to start in Early September.  Fill material will be placed in “lifts” and compacted until the final grade height is reached.

Typical levels of construction noise and vibrations are expected with all of these activities. For the deep foundation work, any possible vibrations will be monitored by a third party testing agency.

Global Administrator | 8/19/2021